# D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 99% complete, FM 512, Hunt County ($10,971,980, 11 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | D. L. Lennon Incorporated - Contractor |
| Subcontractors | Striping Technology, L.P. (2.96%); Texana Land & Asphalt, INC. (2.26%); Texas Traffic And Barricade, LLC (0.45%); Texop Construction (0.12%); Bahena Construction Co., INC. (9.84%); Catocon, INC. (4.5%); J. H. Oden Contracting Company (1.04%); Mojica Construction LLC (2.07%); Morris County Contractors, L.L.C. (2.04%); Southwest Environment Services LLC (0.38%); Silver Creek Construction, INC. (0%) |
| Progress | 98.78% complete, 97.69% of time used |
| Amount | $10,971,980 revised (original $10,425,421) |
| Change orders | $272,509 |
| Paid to date | $10,567,395 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 512, FM 512 from SH 34 to FM 118, Hunt County, Paris District |
| Let / began | 2023-08-02 / 2024-07-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233016 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.