# D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 100% complete, FM 271, Fannin County ($7,545,933, 9 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | D. L. Lennon Incorporated - Contractor |
| Subcontractors | Panola Sign & Barricade, INC. (0.47%); J. H. Oden Contracting Company (2.02%); Bahena Construction Co., INC. (6.41%); Farr Foundation, INC. (0.93%); Southern Cross Contractors, LLC (2.12%); Texana Land & Asphalt, INC. (4.5%); Wims Environmental Construction, LTD. (0.7%); Cold Creek Construction, LTD (2.5%); Trp Construction Group, LLC (1.83%) |
| Progress | 99.89% complete, 85.01% of time used |
| Amount | $7,545,933 revised (original $7,082,890) |
| Change orders | $249,899 |
| Paid to date | $7,324,598 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 271, FM 271 FROM SH 78 TO PR 24, Fannin County, Paris District |
| Let / began | 2022-09-08 / 2022-12-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 9223232 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.