# Dan Williams Company: TxDOT bridge replacement contract 100%+ complete, CS, El Paso County ($2,607,346, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Dan Williams Company |
| Subcontractors | Los Fierro Construction (10.78%); Emery Sapp & Son's INC. (0.47%); Pmi Pavement Marking, LLC (0.27%) |
| Progress | 101.88% complete, 88.27% of time used |
| Amount | $2,607,346 revised (original $2,528,666) |
| Change orders | $41,181 |
| Paid to date | $2,618,159 |
| Work | Bridge Replacement |
| Location | CS, MARIE TOBIN DR to RAYMOND TELLES DR, El Paso County, El Paso District |
| Let / began | 2025-10-08 / 2025-12-15 |
| Latest estimate | 2026-10-02 |
| Contract number | 10253019 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.