# Dan Williams Company: TxDOT bridge replacement contract 100% complete, FM 3351, Comal County ($12,700,475, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Dan Williams Company |
| Subcontractors | Trp Construction Group, LLC (0.69%); King George Traffic Solutions LLC (0.51%); Environmental Safety Services, INC. (3.19%); Houston Sawing & Drilling (0.14%); Lone Star Paving Company (10%); Scott Derr Painting Co, LLC (0.3%); Toro Bravo Construction, LLC (2.82%) |
| Progress | 99.93% complete, 92.03% of time used |
| Amount | $12,700,475 revised (original $12,558,078) |
| Change orders | $142,397 |
| Paid to date | $12,691,309 |
| Work | Bridge Replacement |
| Location | FM 3351, AT CIBOLO CREEK to ., Comal County, San Antonio District |
| Let / began | 2024-02-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 2243205 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.