# Dan Williams Company: TxDOT widen non-freeway contract 53% complete, SS 320, El Paso County ($116,643,363, 9 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Dan Williams Company |
| Subcontractors | Bag Reinforcing LLC (0.98%); Major Motion Logistics, LLC (2.29%); Concrete Pumping, INC. DBA Cpi (0.01%); S&S Contractors, LLC. (0.73%); Tri State Electric, LTD. (14.16%); Penhall Company (0.05%); Border Drilling LLC (0.96%); Pmi Pavement Marking, LLC (0.44%); Scott Derr Painting Co, LLC (1.83%) |
| Progress | 53.2% complete, 29.68% of time used |
| Amount | $116,643,363 revised (original $112,560,911) |
| Change orders | $2,608,801 |
| Paid to date | $61,274,551 |
| Work | Widen Non-Freeway |
| Location | SS 320, FM 3255 to RAILROAD DRIVE, El Paso County, El Paso District |
| Let / began | 2025-05-02 / 2025-07-10 |
| Latest estimate | 2026-10-02 |
| Contract number | 5253237 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.