# Dan Williams Company: TxDOT upgrade to standards freeway contract 66% complete, FM 812, Bastrop County ($7,716,777, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Dan Williams Company |
| Subcontractors | *austin Traffic Signal Construction Co., INC. (2.23%); D. I. J. Construction, INC. (1.74%); Environmental Safety Services, INC. (7.32%); Gbc General Barricade Company LLC (0.26%); Lone Star Paving Company (30.75%) |
| Progress | 65.7% complete, 54.81% of time used |
| Amount | $7,716,777 revised (original $7,601,604) |
| Change orders | $-20,630 |
| Paid to date | $4,980,991 |
| Work | Upgrade To Standards Freeway |
| Location | FM 812, OLD SAN ANTONIO/WATTS LANE to ARTESIAN DRIVE, Bastrop County, Austin District |
| Let / began | 2025-06-04 / 2025-10-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253006 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.