# Dcc Construction And Services, L.L.C.: TxDOT bridge replacement contract 85% complete, CR, Polk County ($3,550,063, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Dcc Construction And Services, L.L.C. |
| Subcontractors | True Roads, LLC (39.91%); Odum Services, LLC (4.04%); M & D Foundation Drilling Industries, INC. (4.05%); J. H. Oden Contracting Company (1.13%); Flex Supply, LLC (1.12%); Carthage Drilling, LLC (12.59%) |
| Progress | 85.34% complete, 93.09% of time used |
| Amount | $3,550,063 revised (original $3,547,063) |
| Paid to date | $3,026,898 |
| Work | Bridge Replacement |
| Location | CR, CARMONA ROAD AT PINEY CREEK to AT PINEY CREEK., Polk County, Lufkin District |
| Let / began | 2024-05-03 / 2025-01-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243221 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.