# Dean Word Company, LTD.: TxDOT overlay contract 44% complete, FM 696, Bastrop County ($6,643,151, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Dean Word Company, LTD. |
| Subcontractors | D. I. J. Construction, INC. (2.18%); Avila And Son's L.L.C. (1.49%); Texas Environmental Management - San Antonio, INC. (1.29%); South Texas Traffic Alliance INC. (3.16%); Professional Traffic Control LLC (0.07%); Eggemeyer Land Clearing, LLC (0.35%) |
| Progress | 44.43% complete, 64.8% of time used |
| Amount | $6,643,151 revised (original $6,445,912) |
| Change orders | $87,778 |
| Paid to date | $2,903,044 |
| Work | Overlay |
| Location | FM 696, US 290 to MUNDINE RD, Bastrop County, Austin District |
| Let / began | 2025-10-08 / 2026-03-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253006 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.