# Dean Word Company, LTD.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 10, Bexar County ($9,012,224, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Dean Word Company, LTD. |
| Subcontractors | Myers Concrete Construction, LP (2.39%); Railpros Field Services, INC. (0.17%); A K Fuquay Construction (0.27%); (Inactive)hogan Murray, INC. (3.4%); Southwest Road & Safety Contractors, LTD. (0.78%); Trp Construction Group, LLC (2.44%); Buyers Barricades San Antonio, LLC (0%); Diibs Specialists, LLC (1.73%) |
| Progress | 100.28% complete, 95.36% of time used |
| Amount | $9,012,224 revised (original $7,922,686) |
| Change orders | $1,089,537 |
| Paid to date | $9,037,482 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 10, SOUTH HACKBERRY ST to IH 410, Bexar County, San Antonio District |
| Let / began | 2025-02-06 / 2025-05-18 |
| Latest estimate | 2026-10-06 |
| Contract number | 2253005 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.