# Deco Contractors, INC.: TxDOT miscellaneous construction contract 89% complete, IH 69, Harris County ($6,961,069, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Deco Contractors, INC. |
| Subcontractors | Creacom, INC. (6.07%); Shaw Drilling, LLC (0.51%) |
| Progress | 88.78% complete, 97.84% of time used |
| Amount | $6,961,069 revised (original $6,683,209) |
| Change orders | $157,859 |
| Paid to date | $6,073,738 |
| Work | Miscellaneous Construction |
| Location | IH 69, IH 10 EAST to LANGLEY ROAD, Harris County, Houston District |
| Let / began | 2025-05-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 5253008 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.