# Delgado's Contractors, LLC: TxDOT bridge replacement contract 100%+ complete, CR, Mills County ($1,525,628, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Delgado's Contractors, LLC |
| Subcontractors | Roadway Traffic Control LLC (1.49%); Vince Construction LLC (9.72%); Jose Santos Construction Company, INC. (1.69%) |
| Progress | 102.41% complete, 120.18% of time used |
| Amount | $1,525,628 revised (original $1,470,000) |
| Change orders | $10,903 |
| Paid to date | $1,516,645 |
| Work | Bridge Replacement |
| Location | CR, CR 508 AT DRAW to ., Mills County, Brownwood District |
| Let / began | 2024-12-03 / 2025-05-08 |
| Latest estimate | 2026-09-29 |
| Contract number | 12243015 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.