# Delhur Industries, INC.: TxDOT widen non-freeway contract 100%+ complete, US 67, Coleman County ($31,047,207, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Delhur Industries, INC. |
| Subcontractors | West Texas Rock Resources, LLC (0.05%); 4-Way Haulers, LLC (3.94%); Contractors Service, LTD. (0.46%); Dk Contracting, LLC (0.41%); Roadway Specialties, INC. (2.72%); Striping Technology, L.P. (0.05%); J. H. Oden Contracting Company (0.18%); Dry River Logistics, LLC (1.67%); Ryan Construction, INC. (0.67%); West Texas Rumble Strip LLC (0.05%); Trp Construction Group, LLC (0.6%); K. L. Durham Construction, L.L.C. (0.23%) |
| Progress | 102.06% complete, 99.86% of time used |
| Amount | $31,047,207 revised (original $27,362,207) |
| Change orders | $2,633,798 |
| Paid to date | $30,613,785 |
| Work | Widen Non-Freeway |
| Location | US 67, BROWN C/L to SANTA ANNA CITY LIMITS, Coleman County, Brownwood District |
| Let / began | 2022-06-02 / 2022-10-10 |
| Latest estimate | 2026-10-01 |
| Contract number | 6223206 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.