# Drake Companies LLC: TxDOT rehabilitation of existing road contract 43% complete, FM 1251, Rusk County ($8,789,708, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Drake Companies LLC |
| Subcontractors | Striping Technology, L.P. (1.98%); Panola Sign & Barricade, INC. (0.4%); Morris County Contractors, L.L.C. (1.04%); J. H. Oden Contracting Company (2.39%); Withers Construction, LLC (7.88%); R & G Construction, LLC (6.94%); Southwest Environment Services LLC (0.67%) |
| Progress | 43.15% complete, 17.54% of time used |
| Amount | $8,789,708 revised (original $8,734,908) |
| Paid to date | $3,769,440 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1251, CR 394 (1.5 MI E OF FM 3135), E to PANOLA C/L (1 MI E OF FM 3231), Rusk County, Tyler District |
| Let / began | 2026-04-07 / 2026-07-20 |
| Latest estimate | 2026-10-02 |
| Contract number | 4263036 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.