# Drake Companies LLC: TxDOT bridge replacement contract 16% complete, SL 323, Smith County ($1,602,227, 6 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Drake Companies LLC |
| Subcontractors | Morris County Contractors, L.L.C. (4.31%); Diamond Elite Barricades, LLC (0.48%); J. H. Oden Contracting Company (1.4%); Striping Technology, L.P. (0.92%); M & D Foundation Drilling Industries, INC. (7.59%); Toro Bravo Construction, LLC (0.36%) |
| Progress | 16.06% complete, 33.85% of time used |
| Amount | $1,602,227 revised (original $1,516,226) |
| Paid to date | $243,447 |
| Work | Bridge Replacement |
| Location | SL 323, 0.12 MI S OF US 271 to UPRR, Smith County, Tyler District |
| Let / began | 2026-04-08 / 2026-09-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 4263237 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.