# Drake Companies LLC: TxDOT rehabilitation of existing road contract 51% complete, US 82, Bowie County ($119,535,649, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Drake Companies LLC |
| Subcontractors | United Concrete Cutting LLC (0.01%); May³ Construction, LLC (1.79%); East Texas Bridge, INC. (0%); J 2 Construction Services, LLC (0.67%); Marcoms Construction LLC (0.25%); Morris County Contractors, L.L.C. (0.33%); Carthage Drilling, LLC (0.02%); Toro Bravo Construction, LLC (0%); H D Aggregates LLC (0.05%); J. H. Oden Contracting Company (1.35%); Scott Derr Painting Co, LLC (0.02%); Skc Earthworks Limited Liability Company (4.24%); Snowhill Contracting LLC (0%); Striping Technology, L.P. (1.79%); Surface Preparation Technologies, LLC (0.13%); Tex Op Construction, LP (0.49%); True Roads, LLC (8.3%); Flex Supply, LLC (0.28%); Antigo Construction, INC. (0.04%) |
| Progress | 50.82% complete, 50.28% of time used |
| Amount | $119,535,649 revised (original $114,513,432) |
| Change orders | $1,082,216 |
| Paid to date | $58,741,441 |
| Work | Rehabilitation Of Existing Road |
| Location | US 82, US 259 to FM 992, Bowie County, Atlanta District |
| Let / began | 2024-08-01 / 2024-11-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 8243052 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.