# Drewery Construction Company, Incorporated: TxDOT overlay contract 100%+ complete, FM 756, Smith County ($3,127,756, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Drewery Construction Company, Incorporated |
| Subcontractors | Southwest Environment Services LLC (1.12%); Morris County Contractors, L.L.C. (0.78%); Red Baron Building Company, LLC (3.73%); Diamond Elite Barricades, LLC (0.19%); Striping Technology, L.P. (5.12%) |
| Progress | 104.36% complete, 113.56% of time used |
| Amount | $3,127,756 revised (original $3,056,756) |
| Change orders | $4,999 |
| Paid to date | $3,195,257 |
| Work | Overlay |
| Location | FM 756, SL 323 to 800 FT N. OF JEFF DAVIS DR., Smith County, Tyler District |
| Let / began | 2026-01-06 / 2026-04-27 |
| Latest estimate | 2026-10-02 |
| Contract number | 1263020 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.