# Drewery Construction Company, Incorporated: TxDOT rehabilitation of existing road contract 96% complete, US 69, Smith County ($8,044,561, 13 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Drewery Construction Company, Incorporated |
| Subcontractors | Panola Sign & Barricade, INC. (1.04%); Southwest Environment Services LLC (0.73%); Striping Technology, L.P. (2.7%); Red Baron Building Company, LLC (0.81%); Cap River LLC (0%); True Roads Construction LLC (2.35%); Aaba Mowing Contractors, Limited Liability Company (0.1%); Surface Preparation Technologies, LLC (0.21%); Jm Yanez Construction, INC. (2.65%); Baker & Company Construction, LLC (10.4%); Innovative Roadway Solutions, LLC (1.13%); Isaacs Construction Services LLC (0.22%); Morris County Contractors, L.L.C. (1.33%) |
| Progress | 96.37% complete, 100% of time used |
| Amount | $8,044,561 revised (original $7,798,138) |
| Change orders | $53,347 |
| Paid to date | $7,566,455 |
| Work | Rehabilitation Of Existing Road |
| Location | US 69, CUMBERLAND RD. to 0.45 MI N OF FM 346, Smith County, Tyler District |
| Let / began | 2023-02-02 / 2023-05-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 2233212 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.