# Duininck, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, US 385, Castro County ($58,052,309, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Duininck, INC. |
| Subcontractors | Hjc Farms, INC. (0.16%); Industrial Fabrics, INC. (7.22%); Jr West Texas Concrete LLC (4.96%); Lmse Trucking, LLC (0.46%); Murray Construction (0.52%); Professional Traffic Control LLC (0.11%); Trp Construction Group, LLC (1.48%); Wims Environmental Construction, LTD. (0.27%); Withers Construction, LLC (0.14%); A Brothers Milling, LLC (0.17%); Artex Electric, INC. (0.48%); H & F Trucking (0.06%) |
| Progress | 100.16% complete, 106.25% of time used |
| Amount | $58,052,309 revised (original $54,353,807) |
| Paid to date | $54,440,026 |
| Work | Rehabilitation Of Existing Road |
| Location | US 385, DEAF SMITH COUNTY LINE to COUNTY ROAD 713, Castro County, Lubbock District |
| Let / began | 2024-02-01 / 2024-05-20 |
| Latest estimate | 2026-10-06 |
| Contract number | 2243002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.