# Duininck, INC.: TxDOT overlay contract 28% complete, SH 207, Hansford County ($12,489,683, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Duininck, INC. |
| Subcontractors | Fc Traffic Control, INC. (0.41%); Lmse Trucking, LLC (0.24%); Dk Contracting, LLC (0.48%); Jr West Texas Concrete LLC (10.92%); Wolfe Construction Group, Incorporated (0.21%); Texop Construction (0.79%); Professional Traffic Control LLC (0.4%); H & F Trucking (0.24%); Texas Panhandle Construction, INC. (1.89%); Surface Preparation Technologies, LLC (0.21%) |
| Progress | 28.13% complete, 66.45% of time used |
| Amount | $12,489,683 revised (original $12,484,683) |
| Paid to date | $3,511,900 |
| Work | Overlay |
| Location | SH 207, HANSFORD CO LINE to CO RD F, Hansford County, Amarillo District |
| Let / began | 2025-09-05 / 2026-05-26 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253204 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.