# Durwood Greene Construction Co.: TxDOT miscellaneous construction contract 91% complete, FM 1097, Montgomery County ($4,950,437, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Durwood Greene Construction Co. |
| Subcontractors | Batterson, LLP (3.87%); Traffic Signs & Lines, LLC (1.96%); Interstate Barricades & Markings, INC. (0.23%); West Texas Rumble Strip LLC (0.44%) |
| Progress | 90.55% complete, 100% of time used |
| Amount | $4,950,437 revised (original $4,872,185) |
| Paid to date | $4,411,896 |
| Work | Miscellaneous Construction |
| Location | FM 1097, SH 75 to WALKER COUNTY LINE, Montgomery County, Houston District |
| Let / began | 2026-01-06 / 2026-04-27 |
| Latest estimate | 2026-10-01 |
| Contract number | 1263013 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.