# Durwood Greene Construction Co.: TxDOT overlay contract 89% complete, BS 35C, Brazoria County ($5,162,601, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Durwood Greene Construction Co. |
| Subcontractors | Professional Traffic Control LLC (0.08%); Interstate Barricades & Markings, INC. (0.19%); East Texas R & D Services, INC. (3.88%); Structural Integrity Group LLC (5.35%); Stripe Lines, INC. (5.38%); Third Coast Services LLC (15.47%); Traffic Signs & Lines, LLC (2.33%); Act Saw Cutting & Removal (0.11%) |
| Progress | 88.76% complete, 64.04% of time used |
| Amount | $5,162,601 revised (original $5,083,723) |
| Change orders | $49,672 |
| Paid to date | $4,556,306 |
| Work | Overlay |
| Location | BS 35C, SH 35 NORTH to FM 1462, Brazoria County, Houston District |
| Let / began | 2025-03-04 / 2025-08-05 |
| Latest estimate | 2026-09-30 |
| Contract number | 3253010 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.