# E-Z Bel Construction, LLC: TxDOT bridge replacement contract 100%+ complete, CR, Matagorda County ($1,854,440, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | E-Z Bel Construction, LLC |
| Subcontractors | Penhall Company (0.62%); Beaird Drilling Services, INC. (13.08%); Sylva Construction, LLC (3.19%); Traffic Signs & Lines, LLC (2.84%); Mb Prime LLC (11.56%); Emery Sapp & Son's INC. (0.62%); Emery Sapp Construction, INC. (0%); Frank Jr Reinforcement LLC (1.16%) |
| Progress | 102.39% complete, 58% of time used |
| Amount | $1,854,440 revised (original $1,833,937) |
| Paid to date | $1,877,768 |
| Work | Bridge Replacement |
| Location | CR, AT LITTLE BOGGY CREEK to STR# AA02-43-001 (S GULF RD), Matagorda County, Yoakum District |
| Let / began | 2025-09-05 / 2026-01-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253227 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.