# Earth Builders, L.P.: TxDOT bridge replacement contract 83% complete, SH 23, Lipscomb County ($18,739,395, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Earth Builders, L.P. |
| Subcontractors | Toro Bravo Construction, LLC (0.31%); Penhall Company (0%); West Texas Rumble Strip LLC (0%); Lanco Turf & Seeding, INC. (0.47%); Morris County Contractors, L.L.C. (1.36%); Fc Traffic Control, INC. (0.07%); M & D Foundation Drilling Industries, INC. (5.79%); Jb Pinnacle Group, LLC (1.71%); S & S Bridge Painting, INC. (0%); Trp Construction Group, LLC (0.34%); Texop Construction (0.06%); Rk Hall, LLC (1.32%); Peachtree Construction, LTD. (0.18%); Emery Sapp & Son's INC. (0.33%) |
| Progress | 83.16% complete, 92.44% of time used |
| Amount | $18,739,395 revised (original $18,726,656) |
| Change orders | $6,739 |
| Paid to date | $15,579,366 |
| Work | Bridge Replacement |
| Location | SH 23, AT GILALOO CREEK to ., Lipscomb County, Amarillo District |
| Let / began | 2025-03-04 / 2025-09-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253006 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.