# East Texas Bridge, INC.: TxDOT overlay contract 46% complete, SL 281, Gregg County ($12,636,645, 4 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | East Texas Bridge, INC. |
| Subcontractors | Striping Technology, L.P. (2.82%); Panola Sign & Barricade, INC. (0.2%); Southern Cross Contractors, LLC (0.89%); Tex Op Construction, LP (2.17%) |
| Progress | 46.35% complete, 36.6% of time used |
| Amount | $12,636,645 revised (original $12,524,243) |
| Paid to date | $5,804,995 |
| Work | Overlay |
| Location | SL 281, 0.54 MI N OF US 80 (SHOFNER DR.) to US 259, Gregg County, Tyler District |
| Let / began | 2025-12-03 / 2026-07-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 12253202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.