# East Texas Bridge, INC.: TxDOT interchange (new or reconstructed) contract 55% complete, US 69, Cherokee County ($68,394,080, 12 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | East Texas Bridge, INC. |
| Subcontractors | Morris County Contractors, L.L.C. (0.52%); Panola Sign & Barricade, INC. (0.28%); Southwest Environment Services LLC (0.17%); Striping Technology, L.P. (1.2%); Texop Construction (0.51%); Withers Construction, LLC (0.77%); Silica Concrete, LLC (0%); Reynolds & Kay, LTD. (0%); Cap River LLC (1.4%); Hodges And Son Construction Company, INC. (0.77%); Isaacs Construction Services LLC (0.34%); Jb Pinnacle Group, LLC (4.27%) |
| Progress | 55.14% complete, 44.61% of time used |
| Amount | $68,394,080 revised (original $66,711,336) |
| Change orders | $907,254 |
| Paid to date | $37,281,780 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 69, 0.5 MI N OF FM 2493-W to 0.5 MI S OF FM 2493-E, Cherokee County, Tyler District |
| Let / began | 2023-08-03 / 2023-10-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 8233274 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.