# Ed Bell Construction Company: TxDOT rehabilitation of existing road contract 40% complete, US 81, Montague County ($20,211,393, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ed Bell Construction Company |
| Subcontractors | Texas Environmental Management - San Antonio, INC. (0.09%); Southern Cross Contractors, LLC (0.17%); Texas Swppp Services (0.39%); Tex Op Construction, LP (2.83%); Eurovia Atlantic Coast LLC (4.76%); Superior Traffic Control, LLC (0.19%); Stripe-A-Zone, LLC (0.6%); Act Saw Cutting & Removal (0.8%); Brenda Price Trucking, INC. (0.25%); Hermanos Steel, LLC (2.75%); Antigo Construction, INC. (1.32%) |
| Progress | 39.9% complete, 44.3% of time used |
| Amount | $20,211,393 revised (original $20,093,159) |
| Change orders | $100,235 |
| Paid to date | $8,056,716 |
| Work | Rehabilitation Of Existing Road |
| Location | US 81, NEAR FRUITLAND ROAD to WISE COUNTY LINE, Montague County, Wichita Falls District |
| Let / began | 2025-10-09 / 2026-02-16 |
| Latest estimate | 2026-10-01 |
| Contract number | 10253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.