# Ed Bell Construction Company: TxDOT upgrade to standards freeway contract 77% complete, US 67, Johnson County ($4,327,072, 13 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Ed Bell Construction Company |
| Subcontractors | Fortson Contracting, INC. (1.72%); Texas Environmental Management - San Antonio, INC. (0.28%); Stripe-A-Zone, LLC (0.86%); Superior Traffic Control, LLC (1.86%); Brenda Price Trucking, INC. (1.16%); Breda Company, INC. (0.16%); Dustrol, INC. (0.25%); Wims Environmental Construction, LTD. (3.09%); Highway Intelligent Traffic Solutions, LLC (0%); Texas Swppp Services (1.41%); Act Saw Cutting & Removal (0.07%); Civil Tree Solutions, LLC (2.69%); Peachtree Construction, LTD. (13.5%) |
| Progress | 76.5% complete, 68.06% of time used |
| Amount | $4,327,072 revised (original $4,249,844) |
| Change orders | $77,221 |
| Paid to date | $3,310,169 |
| Work | Upgrade To Standards Freeway |
| Location | US 67, HIX RD. CR 801B to EXIT RAMP TO FM 2280, Johnson County, Fort Worth District |
| Let / began | 2025-11-05 / 2026-01-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 11253012 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.