# Elecnor Belco Electric, INC.: TxDOT traffic signal contract 25% complete, Various, Bexar County ($1,500,970, 1 sub)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Elecnor Belco Electric, INC. |
| Subcontractors | Fibertel, LLC (0%) |
| Progress | 24.87% complete, 12.69% of time used |
| Amount | $1,500,970 revised (original $1,500,970) |
| Paid to date | $373,259 |
| Work | Traffic Signal |
| Location | Various, DISTRICTWIDE TRAFFIC CONTROL FY 202 to PROJECT 1, Bexar County, San Antonio District |
| Let / began | 2025-02-07 |
| Latest estimate | 2026-10-06 |
| Contract number | 2253223 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.