# Elite Kings Construction, LLC: TxDOT maintenance contract 3% complete, IH0069, Harris County ($5,002,999, 1 sub)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Elite Kings Construction, LLC |
| Subcontractors | Moore Clean LLC (0%) |
| Progress | 3.08% complete, 35.89% of time used |
| Amount | $5,002,999 revised (original $5,003,000) |
| Paid to date | $154,113 |
| Work | Maintenance |
| Location | IH0069, IH 69, ETC. VARIOUS LOCATIONS, Harris County, Houston District |
| Let / began | 2026-03-05 / 2026-05-18 |
| Latest estimate | 2026-10-01 |
| Contract number | 3264201 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.