# Fireman Excavating, INC.: TxDOT maintenance contract 64% complete, IH0030, Dallas County ($51,801,626, 1 sub)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Fireman Excavating, INC. |
| Subcontractors | Brenda Price Trucking, INC. (0%) |
| Progress | 64.13% complete, 60.48% of time used |
| Amount | $51,801,626 revised (original $24,325,136) |
| Change orders | $27,483,360 |
| Paid to date | $33,226,270 |
| Work | Maintenance |
| Location | IH0030, VARIOUS ROADWAYS IN THE EAST DALLAS to COUNTY MAINTENANCE SECTION, Dallas County, Dallas District |
| Let / began | 2024-02-02 / 2024-04-26 |
| Latest estimate | 2026-10-01 |
| Contract number | 2244212 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.