# Fireman Excavating, INC.: TxDOT maintenance contract 54% complete, IH0030, Dallas County ($59,194,641, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Fireman Excavating, INC. |
| Subcontractors | Jackson Excavation, LLC (0%); Peachtree Construction, LTD. (0%); Dustrol, INC. (0%); Nortex Concrete Lift & Stabilization, INC. (0%); O. Trevino Construction, LLC (0%); Sweeping Corporation Of America, LLC (0%); Dallas Lite And Barricade, INC. (0%) |
| Progress | 53.61% complete, 58.42% of time used |
| Amount | $59,194,641 revised (original $26,852,806) |
| Change orders | $32,351,477 |
| Paid to date | $31,738,289 |
| Work | Maintenance |
| Location | IH0030, VARIOUS ROADWAYS IN THE to West Dallas Maint. Section, Dallas County, Dallas District |
| Let / began | 2024-03-06 / 2024-05-26 |
| Latest estimate | 2026-10-05 |
| Contract number | 3244204 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.