# Fireman Excavating, INC.: TxDOT maintenance contract 84% complete, IH0020, Kaufman County ($836,760)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Fireman Excavating, INC. |
| Progress | 83.92% complete, 88% of time used |
| Amount | $836,760 revised (original $608,290) |
| Change orders | $229,225 |
| Paid to date | $702,822 |
| Work | Maintenance |
| Location | IH0020, VARIOUS ROADWAYS IN THE KAUFMAN - to ROCKWALL MAINTENANCE SECTION, Kaufman County, Dallas District |
| Let / began | 2025-07-02 / 2025-09-17 |
| Latest estimate | 2026-09-29 |
| Contract number | 7254205 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.