# Flatiron Constructors, INC.: TxDOT interchange (new or reconstructed) contract 68% complete, IH 35E, Ellis County ($141,836,602, 29 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Flatiron Constructors, INC. |
| Subcontractors | Ejt Trucking, LLC (0%); A Brothers Milling, LLC (0%); A.Z. Rebar Construction, INC. (0%); Jrb Engineering, LLC (0%); Southeast Grinding And Grooving LLC (0%); Buyers Barricades, INC. (0%); USA Swppp Inspections, INC. (0%); Florida Traffic Control Devices, INC. (0%); Act Saw Cutting & Removal (0%); A R Daniel Construction Services, Incorporated (0%); Jb Pinnacle Group, LLC (0%); Wylie Drilling & Drainage, INC. (0%); Fortson Contracting, INC. (0%); Stripe-A-Zone, LLC (0.58%); Chiron Communication Services, LLC (0%); Traffic Highway Maintenance, LLC (0%); G&B Construction Group LLC (0%); Vista Ridge Concrete Pumping, INC. (0%); Davis Motor Crane Service, INC. (0.01%); Farr Foundation, INC. (0.47%); Antigo Construction, INC. (0%); A&E Concrete LLC (0%); Toro Bravo Construction, LLC (0%); Wims Environmental Construction, LTD. (0%); Texas Materials Group, INC. (0%); Road Solutions L.L.C. (0%); J.H. Painting Company (0%); Lindamood, INC. (0%); King George Traffic Solutions LLC (0%) |
| Progress | 67.72% complete, 70.39% of time used |
| Amount | $141,836,602 revised (original $137,121,306) |
| Change orders | $923,896 |
| Paid to date | $93,489,254 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 35E, IH 35E AT FM 664 to & IH 35E AT SL 9, Ellis County, Dallas District |
| Let / began | 2024-02-01 / 2024-06-03 |
| Latest estimate | 2026-10-05 |
| Contract number | 2243001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.