# Florida Traffic Control Devices, INC.: TxDOT traffic signal contract 41% complete, SL 12, Dallas County ($3,352,333, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Florida Traffic Control Devices, INC. |
| Subcontractors | Highway Traffic Control & Services, LLC (0.6%); Jr West Texas Concrete LLC (14.79%); Royal Striping Limited Liability Company (5.66%) |
| Progress | 41.21% complete, 53.33% of time used |
| Amount | $3,352,333 revised (original $3,333,333) |
| Paid to date | $1,373,748 |
| Work | Traffic Signal |
| Location | SL 12, VARIOUS INTERSECTIONS to IN THE CITY OF DALLAS, Dallas County, Dallas District |
| Let / began | 2024-11-06 |
| Latest estimate | 2026-10-01 |
| Contract number | 11243021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.