# Florida Traffic Control Devices, INC.: TxDOT traffic signal contract 91% complete, CS, Collin County ($1,395,950, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Florida Traffic Control Devices, INC. |
| Subcontractors | Royal Striping Limited Liability Company (2.01%); Jr West Texas Concrete LLC (17.48%) |
| Progress | 90.87% complete, 87.27% of time used |
| Amount | $1,395,950 revised (original $1,368,368) |
| Change orders | $17,582 |
| Paid to date | $1,259,363 |
| Work | Traffic Signal |
| Location | CS, VARIOUS INTERSECTIONS to IN THE CITY OF ALLEN, Collin County, Dallas District |
| Let / began | 2024-11-07 |
| Latest estimate | 2026-10-01 |
| Contract number | 11243221 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.