# Fnf Construction, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 20, Reeves County ($32,442,645, 13 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Jvh4 Services, LLC (0.03%); Fc Traffic Control, INC. (0.03%); Aoc Haulers LLC (3.24%); A Brothers Milling, LLC (2.6%); Coughlin Company I, INC. (0.08%); J H Trucking (0.93%); Renteria Brother's Cleaning Service LLC (4.25%); Makin' It Move Transport,LLC (3.34%); The Truesdell Corporation (5.72%); West Texas Rock Resources, LLC (0.11%); Trp Construction Group, LLC (1.39%); Rpv Construction, LLC (2.03%); Dk Contracting, LLC (0.71%) |
| Progress | 104.51% complete, 95.88% of time used |
| Amount | $32,442,645 revised (original $27,943,635) |
| Change orders | $2,803,631 |
| Paid to date | $32,134,190 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, 0.35 MILES W OF CR 210 to 0.15 MI W OF CR 209, Reeves County, Odessa District |
| Let / began | 2024-11-06 / 2025-04-30 |
| Latest estimate | 2026-09-30 |
| Contract number | 11243004 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.