# Fnf Construction, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 20, Reeves County ($36,856,297, 16 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Total Site, INC. (0.05%); Coughlin Company I, INC. (0.14%); West Texas Rock Resources, LLC (0.07%); Fc Traffic Control, INC. (0.03%); A Brothers Milling, LLC (2.7%); Aoc Haulers LLC (3.24%); J H Trucking (2.7%); Makin' It Move Transport,LLC (3.5%); Jvh4 Services, LLC (0.05%); Renteria Brother's Cleaning Service LLC (4.16%); Hjc Farms, INC. (0.39%); Trp Construction Group, LLC (1.39%); Rpv Construction, LLC (1.57%); The Truesdell Corporation (6.38%); Royal Rebar INC (0.02%); Aaron Concrete Contractors, LLC (0.36%) |
| Progress | 105.62% complete, 76.73% of time used |
| Amount | $36,856,297 revised (original $31,497,131) |
| Change orders | $3,512,804 |
| Paid to date | $36,976,055 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, 3.5 MI W OF FM 2903 to 0.35 MI W OF CR 210, Reeves County, Odessa District |
| Let / began | 2024-11-07 / 2025-01-22 |
| Latest estimate | 2026-09-30 |
| Contract number | 11243203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.