# Fnf Construction, INC.: TxDOT safety rest area contract 99% complete, IH 20, Nolan County ($35,368,418, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Mica Corporation (2.35%); Act Saw Cutting & Removal (0.34%); Marcoms Construction LLC (0.6%); Hjc Farms, INC. (1.04%); Willis Electric Co., LP (10.78%); Texas Environmental Management - San Antonio, INC. (0.21%); Toro Bravo Construction, LLC (0.58%); Trp Construction Group, LLC (0.92%); West Texas Rock Resources, LLC (0.01%); Santa Fe Concrete Services LLC (0.83%); W. S. Construction Company (4.69%); Peyson Transport, LLC (0.13%) |
| Progress | 98.93% complete, 95.68% of time used |
| Amount | $35,368,418 revised (original $34,593,730) |
| Change orders | $392,933 |
| Paid to date | $34,610,572 |
| Work | Safety Rest Area |
| Location | IH 20, FROM 0.7 MILES EAST OF CR 226 to 1.9 MILES EAST OF CR 226, Nolan County, Abilene District |
| Let / began | 2024-11-07 / 2025-05-01 |
| Latest estimate | 2026-10-06 |
| Contract number | 11243205 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.