# Fnf Construction, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 20, Reeves County ($67,442,377, 16 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Peyson Transport, LLC (2.06%); Environeer, LLC (0%); Jb Pinnacle Group, LLC (3.69%); Fc Traffic Control, INC. (0.57%); Dustrol, INC. (1.68%); Hjc Farms, INC. (2.65%); S&S Bridge Painting (0.09%); V-Tech Enviromental Services (0.18%); Makin' It Move Transport,LLC (0.62%); 1 Priority Environmental Services, LLC (0%); Texas Cutting & Coring Gp, INC. (0.06%); Wild West Trucking, LLC (5.56%); Scr Civil Construction, LLC (1.5%); West Texas Rock Resources, LLC (0.05%); Renteria Brother's Cleaning Service LLC (0.73%); Trp Construction Group, LLC (1.31%) |
| Progress | 102.05% complete, 99.19% of time used |
| Amount | $67,442,377 revised (original $56,142,249) |
| Change orders | $9,308,502 |
| Paid to date | $66,791,372 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, From Split to 9 m E on IH20 & From Split to 6 m E on IH10, Reeves County, Odessa District |
| Let / began | 2023-02-01 / 2023-07-24 |
| Latest estimate | 2026-09-30 |
| Contract number | 2233001 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.