# Fnf Construction, INC.: TxDOT rehabilitation of existing road contract 94% complete, US 83, Jones County ($39,942,008, 21 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Halligan Services LLC (2.9%); S & S Bridge Painting, INC. (0.03%); Willis Electric Co., LP (2.19%); 4-Way Haulers, LLC (3.32%); Az Grademaker INC (0.58%); Performance Equipment Service (0.94%); Trp Construction Group, LLC (0.69%); Hodges And Son Construction Company, INC. (1.07%); Toro Bravo Construction, LLC (0.22%); Act Saw Cutting & Removal (0.03%); Jb Pinnacle Group, LLC (1.89%); Penhall Company (0.05%); Makin' It Move Transport,LLC (3.12%); Fc Traffic Control, INC. (0.59%); West Texas Rock Resources, LLC (0.01%); Texas Environmental Management - San Antonio, INC. (0.62%); Hjc Farms, INC. (3.27%); Triple B Crane, LLC (0.32%); Tejas Concrete Pumping, LLC (0.08%); Mica Corporation (0.2%); Emery Sapp & Son's INC. (0.05%) |
| Progress | 94.2% complete, 74.24% of time used |
| Amount | $39,942,008 revised (original $39,496,851) |
| Change orders | $138,880 |
| Paid to date | $37,336,704 |
| Work | Rehabilitation Of Existing Road |
| Location | US 83, .67 MILES NORTH OF FM 3034 to .28 MILES SOUTH OF FM 3034, Jones County, Abilene District |
| Let / began | 2024-07-09 / 2025-01-13 |
| Latest estimate | 2026-10-06 |
| Contract number | 7243005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.