# Fnf Construction, INC.: TxDOT rehabilitation of existing road contract 24% complete, US 87, Hartley County ($99,688,127, 13 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Fnf Construction, INC. |
| Subcontractors | Act Saw Cutting & Removal (0.04%); W. S. Construction Company (8.17%); Makin' It Move Transport,LLC (5.23%); Wolfe Construction Group, Incorporated (0.49%); Toro Bravo Construction, LLC (0.04%); Trp Construction Group, LLC (1.18%); Cold Creek Construction, LTD (0.04%); Hjc Farms, INC. (0.35%); Marcom's Mowing Service, LLC (0.57%); Jvh4 Services, LLC (0.29%); West Texas Rumble Strip LLC (0.03%); Apollo Constructors, INC. (0.71%); A. L. Helmcamp, INC. (0.02%) |
| Progress | 23.87% complete, 13.97% of time used |
| Amount | $99,688,127 revised (original $99,678,127) |
| Paid to date | $23,792,385 |
| Work | Rehabilitation Of Existing Road |
| Location | US 87, EAST OF US385/US87 INTERCHANGE to MOORE COUNTY LINE, Hartley County, Amarillo District |
| Let / began | 2025-09-04 / 2026-03-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253001 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.