# Fnh Construction, LLC: TxDOT rehabilitation of existing road contract 100% complete, IH 20, Dallas County ($21,683,466, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Fnh Construction, LLC |
| Subcontractors | Dustrol, INC. (3.55%); Linear Traffic Markings LLC (1.54%); C. Green Scaping, L.P. (0.07%); King George Traffic Solutions LLC (0.1%); Gibson & Associates, INC. (4.82%); Diibs Specialists, LLC (3.88%); Macias Specialty Contracting LLC (0.45%); West Texas Rumble Strip LLC (0.07%); Reliable Concrete Cutting LLC (0.12%); Act Saw Cutting & Removal (0.12%); Penhall Company (0.12%); Paniolo Construction Services, LLC (0.12%); Austin Bridge & Road Services, LP (0.07%) |
| Progress | 99.64% complete, 162.1% of time used |
| Amount | $21,683,466 revised (original $20,222,498) |
| Change orders | $11,668 |
| Paid to date | $20,161,543 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, IH 45 to IH 635, Dallas County, Dallas District |
| Let / began | 2023-06-01 / 2023-11-29 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233004 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.