# Fnh Construction, LLC: TxDOT traffic signal contract 77% complete, SH 199, Tarrant County ($2,915,912, 1 sub)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Fnh Construction, LLC |
| Subcontractors | Road Solutions L.L.C. (37.87%) |
| Progress | 77.47% complete, 233.64% of time used |
| Amount | $2,915,912 revised (original $2,827,960) |
| Change orders | $6,780 |
| Paid to date | $2,196,133 |
| Work | Traffic Signal |
| Location | SH 199, 0.1 MI. NW OF ROBERTS CUT OFF to 0.1 MI. S OF WEATHERFORD ST, Tarrant County, Fort Worth District |
| Let / began | 2024-06-05 / 2025-08-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243027 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.