# Fnh Construction, LLC: TxDOT traffic signal contract 94% complete, SH 183, Tarrant County ($2,328,217, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Fnh Construction, LLC |
| Subcontractors | M. Jones Construction (0.33%); Blue Rock Drilling, LLC (0.74%); American Traffic Construction LLC (0%) |
| Progress | 93.51% complete, 173.19% of time used |
| Amount | $2,328,217 revised (original $2,255,934) |
| Change orders | $26,282 |
| Paid to date | $2,134,074 |
| Work | Traffic Signal |
| Location | SH 183, 0.1 MI S OF GREEN OAKS RD to 0.1 MI N OF GREEN OAKS RD, Tarrant County, Fort Worth District |
| Let / began | 2023-08-03 / 2024-11-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233252 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.