# Forde Construction Company, INC.: TxDOT overlay contract 93% complete, FM 2100, Harris County ($1,831,845, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Forde Construction Company, INC. |
| Subcontractors | Traf-Tex, INC. (4.83%); Emery Sapp & Son's INC. (6.08%); Southwest Road & Safety Contractors, LTD. (3.43%); Williams Road, LLC (2.79%); J & M Contracting, Company (2.28%); Stripe Lines, INC. (7.7%) |
| Progress | 92.83% complete, 78.57% of time used |
| Amount | $1,831,845 revised (original $1,798,696) |
| Change orders | $5,147 |
| Paid to date | $1,674,453 |
| Work | Overlay |
| Location | FM 2100, ULRICH RD to FM 1942, Harris County, Houston District |
| Let / began | 2026-04-07 / 2026-07-07 |
| Latest estimate | 2026-10-12 |
| Contract number | 4263023 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.