# Foremost Paving, INC.: TxDOT widen non-freeway contract 92% complete, SH 107, Hidalgo County ($31,803,780, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Traf-Tex, INC. (4.42%); Soil-Tech, INC. (0.37%); Gp7 Construction INC. (9.04%); Highway Barricades And Services, LLC (1.24%); Rio Grande Rebar Rodbusters, LLC (0.03%); Soil Tech Advance INC. (0.37%); G & E Escobedo Construction, INC. (0%) |
| Progress | 91.87% complete, 103.71% of time used |
| Amount | $31,803,780 revised (original $21,103,891) |
| Change orders | $10,416,301 |
| Paid to date | $28,957,852 |
| Work | Widen Non-Freeway |
| Location | SH 107, FM 493 to US 281 E, Hidalgo County, Pharr District |
| Let / began | 2019-03-06 / 2021-05-03 |
| Latest estimate | 2026-10-02 |
| Contract number | 3193203 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.