# Foremost Paving, INC.: TxDOT new location freeway contract 33% complete, US 77, Kenedy County ($62,380,950, 9 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Southwest Road & Safety Contractors, LTD. (0.91%); Long Legacy Enterprises, LLC (0.16%); Soil Tech Advance INC. (1.21%); Highway Barricades And Services, LLC (0.33%); Texas Highway Systems, INC. (0.08%); *austin Traffic Signal Construction Co., INC. (0.43%); Scott Derr Painting Co, LLC (0.17%); Izaguirre Construction LLC (1.29%); Rio Grande Rebar Rodbusters, LLC (0.1%) |
| Progress | 33.12% complete, 55.19% of time used |
| Amount | $62,380,950 revised (original $61,607,900) |
| Paid to date | $20,402,657 |
| Work | New Location Freeway |
| Location | US 77, 11.40 MILES NORTH OF NORIAS RD to 9.6 MILES NORTH OF NORIAS RD, Kenedy County, Pharr District |
| Let / began | 2025-04-04 / 2025-09-29 |
| Latest estimate | 2026-10-01 |
| Contract number | 4253202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.