# Foremost Paving, INC.: TxDOT rehabilitation of existing road contract 72% complete, SH 285, Jim Hogg County ($37,180,839, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Texas Highway Systems, INC. (0.41%); Soil Tech Advance INC. (1.85%); Laredo Striping, INC. (0.97%); Anderson Columbia Co., INC. (44.98%); Avila And Son's L.L.C. (9.13%); Highway Barricades And Services, LLC (1.66%); *austin Traffic Signal Construction Co., INC. (0.01%) |
| Progress | 71.7% complete, 45.21% of time used |
| Amount | $37,180,839 revised (original $34,775,853) |
| Change orders | $335,994 |
| Paid to date | $25,176,349 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 285, FM 1017 to JIM HOGG/BROOKS CL, Jim Hogg County, Pharr District |
| Let / began | 2024-05-03 / 2024-07-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 5243204 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.