# Foremost Paving, INC.: TxDOT overlay contract 100%+ complete, IH 69C, Hidalgo County ($6,506,834, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Soil Tech Advance INC. (0.12%); Southwest Road & Safety Contractors, LTD. (1.27%); D&G Energy Corporation (1.23%); Highway Barricades And Services, LLC (3.64%) |
| Progress | 103.32% complete, 134.17% of time used |
| Amount | $6,506,834 revised (original $6,414,834) |
| Change orders | $60,000 |
| Paid to date | $6,689,755 |
| Work | Overlay |
| Location | IH 69C, BU 281 to FM 2812, Hidalgo County, Pharr District |
| Let / began | 2025-05-01 / 2025-09-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 5253006 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.