# Foremost Paving, INC.: TxDOT bridge replacement contract 98% complete, FM 2556, Cameron County ($8,273,034, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (4.11%); Highway Barricades And Services, LLC (0.43%); Soil Tech Advance INC. (1.26%); Texas Highway Systems, INC. (0.28%); Aaron Concrete Contractors, LLC (2.87%); Sk Concrete Services LLC (0.16%) |
| Progress | 97.87% complete, 100% of time used |
| Amount | $8,273,034 revised (original $7,945,429) |
| Change orders | $28,686 |
| Paid to date | $7,804,123 |
| Work | Bridge Replacement |
| Location | FM 2556, 2.9 MI N OF US 281 MILITARY to @ ARROYO COLORADO, Cameron County, Pharr District |
| Let / began | 2024-07-09 / 2024-10-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 7243006 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.